SSM_27
Structural
- Jun 17, 2017
- 8
Hello everyone. Why are intermittent groove/butt welds prohibited, with either full or partial penetration? This is specified in the European design code (Eurocode 3). I am not familiar with other standards, but I see this is also specified in AWS D1.1 (4.8.2). Please correct me if I misunderstand. I'm not looking at a particular connection (example), just the reasoning behind it (in principle). Does is have anything to do with the type of loads applied (static or dynamic), fatigue etc. Thank you in advance.