Hi Everyone, I have worked on a few wood frame over concrete podium structures and I always get push back from the contractors to post install anchors for the sill plates and chords. Their issue is coordinating the placement/location of the anchors. My issue is post installing anchors and the risk of cutting the top reinforcement of the concrete slab.
Has anyone else had similar situations and what was the solution?
Has anyone else had similar situations and what was the solution?