I have a small question.

I have a main project and sub projects with tasks for each sub project. For each sub project , the duration for that particular project is wrong for some reason. It shows for example: Nov 30 3:30 PM Dec 4 2:30 AM as 10.38 days.
We are a 24hr operation . To accomodate this i changed all the task information for all tasks to 24 hr in Calander.

Since the sub project's durations are wrong , the main projects duration is wrong.

Please help!
 
Replies continue below

Recommended for you

Do you actually have work hours loaded? You might also need to "refresh" each task, so that the new calendar can take effect.

TTFN

FAQ731-376
 
I figured it out. It had to do with the default hrs set my project ( 8-5) . I changed that and it fixed the hrs and reflected correct days on subprojects.

Thanks for the help though.
 