I have a project with an existing lightweight concrete (3000 psi) slab on metal deck on steel beams. The existing slab has 2 large areas of depressed slabs. One is a 2" depressed slab (11,000 ft^2) and the other is a 3/4" depressed slab (2500 ft^2). Currently there is tile and grout in the 3/4" depression and grout and stone in the 2" depression. Both of these are coming out and being leveled. Both areas are interior office space.
For the 2" slab I am showing a 3000psi N.W. slab infill with 6x6-W2.1xW2.1 WWF and contreol joints centered directly over each of the beams below (~10'-0" o.c).
For the 3/4" slab I am calling for a prepackaged polymer modified mortar (SikaTop 122+) with 1/4" aggregate added to help reduce shrinkage. This area will be carpeted.
For both infills I was calling for the existing slab to be prepared with a scabbler to roughen the surface. Then to clean the surface of all dust, oil, laitance, and bond-inhibiting materials. Then adding a latex bonding grout on the surface prior to pouring the new slab topping.)
Does anyone see anything I should be concerned with? Should I use a stronger epoxy bonding agent?
For the 2" slab I am showing a 3000psi N.W. slab infill with 6x6-W2.1xW2.1 WWF and contreol joints centered directly over each of the beams below (~10'-0" o.c).
For the 3/4" slab I am calling for a prepackaged polymer modified mortar (SikaTop 122+) with 1/4" aggregate added to help reduce shrinkage. This area will be carpeted.
For both infills I was calling for the existing slab to be prepared with a scabbler to roughen the surface. Then to clean the surface of all dust, oil, laitance, and bond-inhibiting materials. Then adding a latex bonding grout on the surface prior to pouring the new slab topping.)
Does anyone see anything I should be concerned with? Should I use a stronger epoxy bonding agent?