struggle66
Civil/Environmental
Hi good day everyone,
I have an existing suspended slab that needs to be topped up by concrete (attached sketch 1). It is a vehicular ramp with L.L = 15 kN/m2. I have considered 2 options.
(1) Consider the lightweight concrete topping as additional dead load and strengthen the existing slab below.
(2) Design a completely new slab (sketch 2).
But I still want explore and study one more option which is to design the concrete topping as structure & take some loadings. Is it possible?
OR
Roughen the existing slab surface so that existing slab & topping will become one slab with total depth 1150mm. Can it be?
How do guys normally do?
I will be thankful if I can have your advice or reference or example.
I have an existing suspended slab that needs to be topped up by concrete (attached sketch 1). It is a vehicular ramp with L.L = 15 kN/m2. I have considered 2 options.
(1) Consider the lightweight concrete topping as additional dead load and strengthen the existing slab below.
(2) Design a completely new slab (sketch 2).
But I still want explore and study one more option which is to design the concrete topping as structure & take some loadings. Is it possible?
OR
Roughen the existing slab surface so that existing slab & topping will become one slab with total depth 1150mm. Can it be?
How do guys normally do?
I will be thankful if I can have your advice or reference or example.