Hi,
There is an existing unreinforced slab on grade that has some light cracks. Expansion joints are spaced about 12 ft in both directions. A new slab on grade is planned to be placed on top of this existing one. We have two options in mind, but not sure which one would be the best. See attached drawing.
In both cases, new sawcut joints will coincide with existing expansion joints.
I will appreciate your advice.
There is an existing unreinforced slab on grade that has some light cracks. Expansion joints are spaced about 12 ft in both directions. A new slab on grade is planned to be placed on top of this existing one. We have two options in mind, but not sure which one would be the best. See attached drawing.
In both cases, new sawcut joints will coincide with existing expansion joints.
I will appreciate your advice.