You may be able to slip line the tunnel with a pipe that is not attacked by the chlorine. Then pressure grout the annular space between the pipe and old tunnel.
There are a few "rubberized" inserts to seal the adjusting rings, both inside MH and outside. That said find out what the Waste water people use on the MH's.
If the main pressure is 170 psi, the fixtures in building hooked up to it would be blowing fixtures all over. The main is probably 10 feet deep so the pressure at the hydrant may be 5 psi less due to the lift to the hydrant.
Look for a couple hog or beef farms near your area. check with them to see if they would take the seaweed. then they can supply the trailer? to haul it back to there feedlot. Should be cheaper to drag the weeds to a spot that they can get to. You may have to help with the loading.