Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. icebloom

    Stiffener & Doubler weld

    AISC has requirements like the spacing of the intermittent welds both longitudinally, transversely, etc in built up members.
  2. icebloom

    About steel beam and shear wall combinations in high-rise buildings

    It is very difficult to moment connect to the core because of concrete breakout issues due to tension in anchors from the bending - especially in thinner walls and where you have no transverse reinforcement (eg ties in the wall). You can do things like welded rebar with extra reinforcement, but...
  3. icebloom

    Point loading on composite deck, mid-span?

    If it is a concentrated load, punching shear should also be checked. Some manufacturers have guidelines on small nominal loads that can be supported. For larger loads a punching check should be conducted. Eurocode and Australian code have specs showing how to determine the effective punching...
  4. icebloom

    Anchor bolt embedment close to edge

    It depends on the context - some designs have ungrouted baseplates where the anchors are fixed to the endplate with a nut either side and there is a gap between this and the substrate. In this case the compression is transferred via the anchors themselves which can cause a punching failure...
  5. icebloom

    Pinned connection of composite beams to shear walls

    It is difficult to moment connect these kinds of beams to a core wall. Often these connections have cleats with horizontally slotted holes to allow for installation tolerances and movement of the core, which also releases them axially. The concrete slab above is relied upon for diaphragm forces...
  6. icebloom

    Anchor bolt embedment close to edge

    It has an effect if your anchor is under compression, in which case the back can punch out. The tension capacity of the anchor is independent of the thickness of the member for the scenario you have shown - it only depends on embedment depth (breakout) and the bearing area at the head of your...
  7. icebloom

    Design of L or J shaped concrete anchor

    The net force on the engaged segment of concrete is still F acting towards the edge regardless of how it is internally resolved by the kinking of the anchor. The segment of concrete engaged will be based on the embedment depth of the anchor, which if anything would be deeper were it straight...
  8. icebloom

    Increasing Capacity of Steel Shear Connection

    If the connection is already under decent load, then swapping the bolts out for higher grade bolts might be difficult if some deformation has already occured and they are jammed in shear. What is the governing the failure mode currently? This may impact the strengthening chosen. And how much...
  9. icebloom

    Welding of high strength grade 8.8 steel bolts

    Thanks for the references Tmoose I will have a look
  10. icebloom

    Connecting Wide flange beam to a Beam reinforced with WT section at bottom

    Another connection you can try is a hanging endplate connection or some variant of this. Variants of this connection would involve either adding gusset above the new beam, or below your WT section to get additional connectivity to the endplate. If highly loaded you tend to get a bit of...
  11. icebloom

    Embedded item in to slab

    Hopefully you've got a deep enough embedment or potentially you could form a pry-out kind of failure surface similar to that of anchors to concrete. Cast in plates with welded rebar like KootK along with vertical ties would help. I don't know if the rebar through drilled holes will do too much...
  12. icebloom

    Fillet weld in compression

    For more lightly loaded connections we typically check that the welds can take the compression which usually is not a problem - if there is a small gap left during fabrication the weld will just yield and you will get contact with the baseplate. The key is to avoid fracture of the weld in other...
  13. icebloom

    ACI 17.6.2.1.3 - Concrete Tension breakout Strength

    See below snapshot of my understanding. Blue is washer and red is the anchor head - by capping the section based on the plate/washer thickness I think the clause is basically giving you a 45 degree dispersion angle (pink) through the washer/plate for which you can claim the effective perimeter...
  14. icebloom

    Composite Column Shear Studs

    Theoretically composite columns can develop full capacity as long as there is enough bond strength between the steel and concrete component (for which there are equations in various standards). If at any location the bond strength is insufficient eg due to load introduction at floor level, then...
  15. icebloom

    Reduce concrete creep

    If designing the slab the engineer would include the effects of creep and shrinkage in the deflection check. Usually at the top of glazing there is also some kind of movement joint which will allow a certain amount of vertical movement of the slab, such that the glass isn't loaded and does not...
  16. icebloom

    HSS column design with shear plate connection

    Yes, we account for eccentricity in the column design either based on the code minimum eccentricity or if say for whatever reason you've got a really eccentric connection then that may govern and cause a larger moment. For typical connections eg shear tab with bolts welded to a column we design...
  17. icebloom

    HSS column design with shear plate connection

    In Australia where I practice the steel code mandates a minimum eccentricity at which shear loads have to be applied to columns, generating a minimum bending moment to include in the column design. In the case of a column continuous above/below the beam level, you can distribute this into the...
  18. icebloom

    Options for dealing with pryout failure (CSA A23.3)

    I've attached the derivation of the pryout capacity equation where it talks about how the typical pryout capacity is obtained including the 40% tension and 60-70% cone size etc, which is what my answer above was based on. Based on a semi tension cone failure surface (note this might also...
  19. icebloom

    Options for dealing with pryout failure (CSA A23.3)

    The paper I was referring to is "A new model for concrete edge failure of multiple row anchorages with supplementary reinforcement—Reinforcement failure" by Sharma et al (it is a fib Technical Paper, https://doi.org/10.1002/suco.201700002). They use an uplift restraint to preclude failure due...
  20. icebloom

    Welding of high strength grade 8.8 steel bolts

    Thanks for the replies guys. Kingnero I will have a further look around about the hydrogen cracking you mention, and the formation of martensite. Tmoose as per my post I am not actually trying to weld the bolts, just understand more the reasoning about what actually happens to the material...

Part and Inventory Search