Background
leaking was found on tube (Supplied By Part Manufacture) during we fill in the water prior to HT on Field. So Eng.Contractor(That Responsible on design) decide to repair the things, assist by the part Manufacture/fabricator of water wall tube. Form P4 was completed sign off by AI...
I have read the Definition before..but the definition also not clear for me..myb not for you.that y i asking..if you think this post waste yr time..i feel sorry..because on actual situation there are arguement between my client..because my rt film not full cover on the haz area due to the weld...
Good day All,
Just 2 simple question regarding RT film interperation.
1) Could any expert explain 'area of interest' inside asme V.
2) is it any paragraph inside asme V, mention RT film should/shall cover the HAZ area.
Tqvm expert.
Muhammad86
Dear all expert,
I got one query regarding mock up test on tube to tubesheet
Welding. How to determine the minimum leak path thickness during review the macro result.Should we refer back to design or we can measure from the macro result. Because during reviewed the report, and porosity was...
Dear All Expert,
I got 1 query regarding UT Scan at 50% completed weld? Purpose i want to conduct UT at 50% completed joint due to it is critical joint and want to avoid defect on early stage. The base material thickness is 50mm, weld completed around 20mm.
Newbie,
Regards,
dear all,
I have 1 question here about unlisted material according to aws d1.1..is it S355jr and S355j2 is the same of unlisted material...because my WPS is s355jr and the actual production is s355j2... So can i proceed using the s355jr wps.
Thank you.
Regards,
Dear All expert,
Any1 who have an experience in AWS Standard. is it true we can built 2 WPS using 1 PQR? same like asme code? which clause should i refer to? because i can't found in section 4.
Thank you.
Regards,
the situation is like this, welder A is a performed GTAW for root&hot pass and welder B performed FCAW for fill&cap at 1 test coupon. i already refer to AWS D1.1, but i didn't see any sentences for weld metal deposit.
newbie engineer
Thanks ron,
But which clause i should refer to..because AWS D1.1 doesn't show at essential for welder. Maybe u can give me the hint why can't...
Just seekig some advise.
newbie engineer
All,
Can I qualified the 2 welder using 1 test coupon only according to AWS D1.1? Which clause i should refer to? is it the trade designation equal to trade name?