Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  • Users: eyec
  • Order by date
  1. eyec

    PIPING INSPECTOR CERTIFICATION

    the proper term is Aramco APPROVED inspector not Aramco CERTIFIED inspector
  2. eyec

    Question re: Travel Speed & AWS D1.1

    maybe they are looking @ the heat input. what material will you be welding?
  3. eyec

    Defining ISO9001 clauses on Validation and Verification in the context of pressure vessels

    in very basic terms you have your assumptions reversed: Validation is the assurance that a product (or service) meets its user's requirements, i.e. calcs for a pressure vesel design. Verification is the determination of a product's (or service's) conformance to original specifications, i.e...
  4. eyec

    Shell TAT/TAMAP list.

    try the link belowhttp://files.engineering.com/getfile.aspx?folder=c237a36e-6fcd-47ef-bed5-54b8e40f7716&file=Appendix_B_Approved_List_of_Materials.pdf
  5. eyec

    machining witness or reference point explanation;

    Mfgenggear, i agree and understand the machining methods you mention, but i have performed many searches and not found a document to reference. i guess i will put it on the engineer and machine shop to answer how they can assure planarity prior to placing the equipment onto the pedestals...
  6. eyec

    machining witness or reference point explanation;

    mfgenggear, no place on the bottom was machined each skid weighs 16tons, so flipping the skid becomes a problem. mikehalloran, to complicate the issue, i have 6 pedestals @ different heights (3 pairs)and piping connections that have to match up to existing piping. so leveling to such tight...
  7. eyec

    Steam Reheater Mystery Marks

    i am assuming that this is a relatively new construction. i agree with the inspectors except for the 3rd picture of the bend. i would say that is a thermal crack. regardless, if you did not find evidence of FOD (foreign object damage), like loose material in the bottom of the vessel, i would...
  8. eyec

    machining witness or reference point explanation;

    Mike, thanks for the response. what you have described is what i have observed over the years. my quandry is, i was looking at a skid that has some pedestals welded on it and the tops had to be machined "flat & true" to the base of the skid (within .001"). however, the drawing nor the skid...
  9. eyec

    machining witness or reference point explanation;

    (not for CNC programing, i have already read up of zero reference points - tool, machine & part) but to establish a beginning point in relationship to the whole part? i am not a machinist but have seen some machining operations and heard machinists use the term witness point or reference point...
  10. eyec

    What do you charge for a second site visit?

    i normally call to confirm any site visits. the cost of a phone call beats the hassle you go thru in your situation.
  11. eyec

    in-process NDE requirements question

    stanweld - agree & have heard the PO reasons for not doing NDE, even informational weldtek - agree on the Minimum requirements. seems butt welds are covered more than any other type of welds for NDE & i do not seem to have the same uphill battle with Sec VIII fabricators/buyers
  12. eyec

    in-process NDE requirements question

    FYI, i did look @ B31.3 344.7 and it says "when specified in the engineering design". may original question remains. gtaw, your post is why i asked this question. i cannot seem to get it thru to some that a little in-process NDE is cheap compared to rejects or failures or safety
  13. eyec

    in-process NDE requirements question

    does any Code prescribe or require in-process NDE (mt, pt,ut,etc)? i have searched various Codes and cannot find any requirements. everything i see is for final inspection. TIA
  14. eyec

    Super Duplex Welding Requirement

    a better forum would have been Welding,Bonding & Fastener Engineering. a search on the internet would have found . . . Link
  15. eyec

    KKS (Siemens) to ANSI (General Electric) equipment description

    convert them both to IEEE 806. it may take a lot of work but i was involved in converting KKS into the equipment catalog system the company used.
  16. eyec

    MT indication acceptance criteria vs inspector level rating

    what did you specify when you purchased the shaft; any acceptance criteria, Standard to meet, your own specification? the vendor may just be wanting to increase the price of meeting your requirements. vendor standard and customer standard are some times cause for additional measures (costs).
  17. eyec

    Wind Farms Cause Climate Change

    Telegraph

Part and Inventory Search