JJMEI
Structural
- Jul 9, 2016
- 12
I am trying to come up with a clever way to connect (2) C15X33.9 so that there is at least a 3" gap for insulation. The reason for this is that one channel is exposed and only for aesthetics while the inside channel is structural. The 3" gap is supposed to create a thermal break as required by the energy code. What is the easiest most efficient way to connect these sections and still have a sufficient thermal break also, I would like to utilize the combined moment of inertia in the horizontal direction for lateral deflection criteria. Connected to the outside channel is 20 feet of storefront. What type of connection would allow me to do this? Has anyone ever dealt with this situation before? I appreciate the free consulting, by the way I'm an engineer in training.