Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Concrete curing of Foundations

Status
Not open for further replies.

PEFLWI

Structural
Oct 23, 2012
120
How long should concrete spread foundations cure before they are backfilled?
 
Replies continue below

Recommended for you

Depends on a lot.....temperature, humidity, curing process, construction sequencing, steel erection, etc.

I would say a minimum of 3 days with good cylinder breaks, but otherwise 7 days or until 75% of f'c is obtained.

 
Assuming 30mpa concrete and normal compaction equipment, 3 days should give you about 15mpa strength. Plenty of capacity. Ask for 3 day cylinder results before compaction.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor