blights
Civil/Environmental
- Jun 11, 2015
- 8
Hello
I would like to ask what is the reason that in practice, when someone is making concrete manually (not from the concrete plant) and wants to make let's say 1 m3 concrete it is required to use more aggregates that when summed up would give 1,2 - 1,4 m3 alone. I'm a student and in the lab we've been doing only the lab method, where everything is weighted and we also check the water content of the materials and subtract the aggregates water from the total water to be added. However, we dimension having 1 m3 in total in the end and not more. What's the reason for this big difference between this methods?
Thanks for the help
I would like to ask what is the reason that in practice, when someone is making concrete manually (not from the concrete plant) and wants to make let's say 1 m3 concrete it is required to use more aggregates that when summed up would give 1,2 - 1,4 m3 alone. I'm a student and in the lab we've been doing only the lab method, where everything is weighted and we also check the water content of the materials and subtract the aggregates water from the total water to be added. However, we dimension having 1 m3 in total in the end and not more. What's the reason for this big difference between this methods?
Thanks for the help