s0eebuch
Mechanical
- Sep 24, 2004
- 71
Hey all,
I'm back! Ok, so here's the deal: My first buried waterline design project for a local county Utility Dept. went out for bid and the response was tremendous (the result of a slow economy, I guess).
So, after doing our due diligence, we accept the lowest bid and award the project. Later, the contractor learned he was the lowest bidder by a significant amount (i.e. He left almost $100K on the table - his bid was that much lower than the next bid).
Now, he's looking to recoup some costs. He is going through my contract documents with a fine-tooth comb, looking to justify a change-order and he hasn't even broke ground yet!
The estimator, "Frank", is a real piece of work too. He's abrupt to the point of rude, confrontational, and gets very defensive at any question/request. In our preconstruction meeting, he demanded the start date of the project get pushed out 14 days. It was (and continues to be) very unpleasant.
Any others notice a trend in how contractors are responding to the engineers? Any tips on how to handle them? Every time Frank calls me, I get tense and find myself at a loss for words. Logic has always served me well and I have a hard time dealing with angry people that will not listen to logic.
Thanks in advance.
I'm back! Ok, so here's the deal: My first buried waterline design project for a local county Utility Dept. went out for bid and the response was tremendous (the result of a slow economy, I guess).
So, after doing our due diligence, we accept the lowest bid and award the project. Later, the contractor learned he was the lowest bidder by a significant amount (i.e. He left almost $100K on the table - his bid was that much lower than the next bid).
Now, he's looking to recoup some costs. He is going through my contract documents with a fine-tooth comb, looking to justify a change-order and he hasn't even broke ground yet!
The estimator, "Frank", is a real piece of work too. He's abrupt to the point of rude, confrontational, and gets very defensive at any question/request. In our preconstruction meeting, he demanded the start date of the project get pushed out 14 days. It was (and continues to be) very unpleasant.
Any others notice a trend in how contractors are responding to the engineers? Any tips on how to handle them? Every time Frank calls me, I get tense and find myself at a loss for words. Logic has always served me well and I have a hard time dealing with angry people that will not listen to logic.
Thanks in advance.