Kottam
Chemical
- Feb 21, 2013
- 5
Hi All,
Fire water system of the offshore platform designed with monitors. The monitors are located away from the deluge skid, the piping between the akid and monitor is air filled. It is observed water hammer pressure during air evacuation from the system. what kind of pressure mitigation measure is the best solution here?
I really appreciate your reply.
Thank you.
Regards,
RR
Fire water system of the offshore platform designed with monitors. The monitors are located away from the deluge skid, the piping between the akid and monitor is air filled. It is observed water hammer pressure during air evacuation from the system. what kind of pressure mitigation measure is the best solution here?
I really appreciate your reply.
Thank you.
Regards,
RR