It has come to my attention that our tooling is being inspected using the same three points to establish the primary, secondary and tertiary datums. I checked Y14.5-1994, and it does not specify that datum points need to be unique.
I have not seen this on a drawing before, and was wondering if it is indeed allowed per the standard, or just our inspection departments own interpretation. We are at the point of revisiting our company standards, and this is becoming a sticking point. Thanks in advance!
Believe it if you need it or leave it if you dare. - [small]Robert Hunter[/small]
I have not seen this on a drawing before, and was wondering if it is indeed allowed per the standard, or just our inspection departments own interpretation. We are at the point of revisiting our company standards, and this is becoming a sticking point. Thanks in advance!
Believe it if you need it or leave it if you dare. - [small]Robert Hunter[/small]