Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations SSS148 on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

instrument legend "Mo3" question in the P&ID

Status
Not open for further replies.

koba78

Petroleum
May 10, 2011
30
Dear eng-tips member

I found a "Mo3" (express as middle of three values is used for alarms and downstream function ) located outside of the instrument circle in our project P&ID, but I don't get it why this should be
there, and it seems unnecessary. Could you please give me some
good explanation for this ?

Thank you very much.
 
Replies continue below

Recommended for you

Its a lazy way to determine an average. This is fairly common to use with interlocks it is intended to prevent false shutdowns (or alarms) based on an erroneous data point.
 
I've not put stuff like that on P&IDs because it can easily change then you have the hassle of MOC. The older guys trained us to not put stuff that easily changes on P&IDs such as set points, alarm points, etc. Just acknowledge the alarms through instrument bubbles and call it good. The younger generation wants to put all kinds of just on P&IDs because they have no desire to look beyond those. Well, at some point you're going to need loops, elementaries, control narratives, logic diagrams, etc.

I am not a fan of it but if they have the clout to put logic, alarm points, etc. on them, they can knock themselves out. I fought that battle and lost. They didn't even want to reference other drawings on P&IDs. But, I digress into minutia.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor