Hi
I am doing a study on intelligent pigging. We are laying a new 22" pipeline and tying into an existing line with a Wye piece.
I line will need pigging to determine corrosion loss during its life
Towards the end of field life, velocities of oil are going to be very low (0.1 m/s or less)
Is there a minimum velocity that an intelligent (MFL) pig can run?
I am doing a study on intelligent pigging. We are laying a new 22" pipeline and tying into an existing line with a Wye piece.
I line will need pigging to determine corrosion loss during its life
Towards the end of field life, velocities of oil are going to be very low (0.1 m/s or less)
Is there a minimum velocity that an intelligent (MFL) pig can run?