struct_eeyore
Structural
- Feb 21, 2017
- 253
Currently designing a small 6' retaining wall. Contractor is requesting we allow him to pour the stem after 3 days. I've never seen any work done before the 7 day mark, and have not been able to locate anything in ACI or IBC regarding this - so hoping someone might point me in the right direction. Now, the stem comes out to about 88 lbs/ft on a 4'Wx1'D footer, and intuitively, having a guy stand on the footer ever 2 feet does not seem like a problem - at 3 days - (obviously back-fill will not be in). What are your thoughts?