Hello,

I'm looking to standardize a practice for cable abandoning in my company.
is there any common practice for this?
I'm specifically interested in cables that were cut at the end point (at a transformer terminals for example).
do you short the phases?
do you ground the phases?
maybe both?

thanks!
 
Replies continue below

Recommended for you

I think it boils down to this. Low quality contractors and plants with poor configuration management will leave the cables in place. Of course, direct buried needs additional consideration. Jim
 