Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations SSS148 on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Nozzle welds

Status
Not open for further replies.

Corgas

Materials
Dec 22, 2008
115
Vessel is being built according to ASME Section VIII Div 1.

Contractor came back saying that above mentioned code does not specify UT for nozzles.

I've alwyays thought that Nozzle-to-shell penetration welds shall be 100% UT examined.

Contractor is proposing use of MT and PT in lieu of UT.

By the way, our spec calls for 100%UT but this in not my area of expertise.

Thanks
 
Replies continue below

Recommended for you

Per Sect. VIII, even 'Full RT' vessels do not require nozzles to be radiographed [RT] or UT'd. That requirement is solely driven by the Customer. Having said that, I would spec. nozz UT on any of my big-bore nozz's on any 100% RT vessel. It finds side-wall Lack-of-Fusion exceptionally well, which is the predominate defect, in my experience.

MT/PT of root and cap is a very poor substitute for UT of the full thickness of the weld. In reality, you are better off with an attentive welding inspector, 3rd-Party CWI prefferably, signing off on the fit-up and root of each nozz, and performing frequent [several times an hour] in-process welding inspections. 100% visual inspection 'VT' is MUCH better than MT/PT of the root [w/o seeing the fit-up], and MT/PT of the cap. Additionally, MT/PT is typically done by an NDT tech, who may not have any training in visual inspection of welds. You need a CWI.
 
Nozzle to shell welds under ASME VIII, Div. 1 do not require RT or UT examination - only visual. If you wish them to be examined by other methods, they must be specified in your Purchase Documents.

 
Status
Not open for further replies.

Part and Inventory Search

Sponsor