raisie
Mechanical
- Dec 23, 2014
- 11
Hi guys.
I have a situation I would appreciate some help on.
There are two gasoline storage tanks (Tank 1 and Tank 2), two pumps (Pump 1 and Pump 2). Currently, Tank 1 and Tank 2 are connected to Pump 1 through a 4 inch pipeline. For future operation purposes, an additional connection will be made from Tank 1 and Tank 2 to Pump 2. Thus, in the future operation mode, fuel will be supplied to from either Tank 1 or Tank 2 to both pumps simultaneously. This means that, in order to deliver the nominal flow to both pumps, the flow through the 4 inch pipeline will double. My colleagues seem to think that the 4 inch pipeline will have to be replaced with a 6 inch pipeline in order to optimally deliver fuel to both pumps and are trying to justify this thought with calculations. With “optimally” I mean that both pumps receive a flow rate equal to their nominal flow rate continuously. The question is, which calculations do you perform to check this??? (Please see the attached sketch)
I think that the size of the pipeline has nothing to do with whether or not both pumps can be provided with their nominal flow, because once the pipelines are filled with fuel and the tank has enough fuel, the pumps will just keep receiving the needed flow through suction. However, I think that due to the doubled amount of required fuel flowing through the same size pipeline, the speed of the flow will be larger and THAT is why the size of the pipeline must be increased. So basically, now I’m looking for a code/standard which specifies recommended speeds of fuels through pipelines.
Am I right on this so far??
I have a situation I would appreciate some help on.
There are two gasoline storage tanks (Tank 1 and Tank 2), two pumps (Pump 1 and Pump 2). Currently, Tank 1 and Tank 2 are connected to Pump 1 through a 4 inch pipeline. For future operation purposes, an additional connection will be made from Tank 1 and Tank 2 to Pump 2. Thus, in the future operation mode, fuel will be supplied to from either Tank 1 or Tank 2 to both pumps simultaneously. This means that, in order to deliver the nominal flow to both pumps, the flow through the 4 inch pipeline will double. My colleagues seem to think that the 4 inch pipeline will have to be replaced with a 6 inch pipeline in order to optimally deliver fuel to both pumps and are trying to justify this thought with calculations. With “optimally” I mean that both pumps receive a flow rate equal to their nominal flow rate continuously. The question is, which calculations do you perform to check this??? (Please see the attached sketch)
I think that the size of the pipeline has nothing to do with whether or not both pumps can be provided with their nominal flow, because once the pipelines are filled with fuel and the tank has enough fuel, the pumps will just keep receiving the needed flow through suction. However, I think that due to the doubled amount of required fuel flowing through the same size pipeline, the speed of the flow will be larger and THAT is why the size of the pipeline must be increased. So basically, now I’m looking for a code/standard which specifies recommended speeds of fuels through pipelines.
Am I right on this so far??