msquared48
Structural
- Aug 7, 2007
- 14,745
Involved in a project where the local plan reviewer (only one for the Jurisdiction) is requiring testing on all concrete over 2500 psi, approved mix design or not..
He is also in the field inspecting with the local inspector (Only one of those too!).
This requirement is causing all sorts of headaches and delays in projects for local contractors.
We normally do not require testing unless the required mix is over 2500psi.
Anyone having similar problems with the plan reviewers?
Mike McCann, PE, SE (WA)
He is also in the field inspecting with the local inspector (Only one of those too!).
This requirement is causing all sorts of headaches and delays in projects for local contractors.
We normally do not require testing unless the required mix is over 2500psi.
Anyone having similar problems with the plan reviewers?
Mike McCann, PE, SE (WA)