psychedomination
Structural
- Jan 21, 2016
- 123
Hi there,
I am a graduate engineer and am working on a basement project. I am dealing with a retaining wall that was recently constructed by a contractor. The wall is a 6” masonry concrete block wall with T12s at 16” centres that was built up to the underside of the upper floor slab. The height of the wall from the top to the bottom of the foundation is about 9’.
I am assuming that the dead load from the upper floor can not be considered to stabilise the wall because when the 6” wall was constructed it did not have a proper bearing interface at the connection to take the dead load.
With this said I analysed the wall as a standard cantilever retaining wall. I do not have much knowledge in masonry design but seeing as concrete blocks were used and the cells were filled with concrete I analysed the wall like a standard concrete retaining wall. I found that the footing was too small for the overturning moment and the vertical steel reinforcement in the wall stem was inadequate.
A fix that I am proposing is to construct pilasters spaced at ~1m (3’) against the 6” wall. These pilasters would take the overturning moment and the bending in the stem and would cause the 6” wall to span horizontally between the pilasters instead of vertically between the floor slabs. As for connecting the pilaster to the existing wall I am thinking of anchoring the pilaster ties into the 6” wall using an epoxy adhesive. The pilaster ties would end up being U shaped bars doweled and epoxied into the 6” wall.
Is a spacing of 1m too small? I am thinking that this can be increased, perhaps to a limit of 6’ depending on the wall capacity (also needs to be small enough to ensure the wall mainly spans between the pilasters). To determine this would I just find out what the distance a 6” concrete slab can span before needing horizontal reinforcement (the 6” wall only has the vertical bars so it has no contribution from horizontal bars)?
Also can it be safe to assume and design these pilasters to act as columns that will take the full overturning moment and bending moment from the vertical direction that the wall was originally meant to take?
Also as shown in the sketch the external wall is resting on some compacted sand (quite hard material, needs a jack hammer or something to break it). I assume I will need to take the vertical load from the external wall on that piece of sandy material as a surcharge acting on the 6” wall also when determining the bending moment in the stem and overturning moment? Please correct me if I am wrong.
I am trying to completely avoid demolishing the existing wall and would prefer to reinforce it some way. The architect is fine with the addition of pilasters.
Any ideas or feedback/advice for this method would be greatly appreciated.
I am a graduate engineer and am working on a basement project. I am dealing with a retaining wall that was recently constructed by a contractor. The wall is a 6” masonry concrete block wall with T12s at 16” centres that was built up to the underside of the upper floor slab. The height of the wall from the top to the bottom of the foundation is about 9’.
I am assuming that the dead load from the upper floor can not be considered to stabilise the wall because when the 6” wall was constructed it did not have a proper bearing interface at the connection to take the dead load.
With this said I analysed the wall as a standard cantilever retaining wall. I do not have much knowledge in masonry design but seeing as concrete blocks were used and the cells were filled with concrete I analysed the wall like a standard concrete retaining wall. I found that the footing was too small for the overturning moment and the vertical steel reinforcement in the wall stem was inadequate.
A fix that I am proposing is to construct pilasters spaced at ~1m (3’) against the 6” wall. These pilasters would take the overturning moment and the bending in the stem and would cause the 6” wall to span horizontally between the pilasters instead of vertically between the floor slabs. As for connecting the pilaster to the existing wall I am thinking of anchoring the pilaster ties into the 6” wall using an epoxy adhesive. The pilaster ties would end up being U shaped bars doweled and epoxied into the 6” wall.
Is a spacing of 1m too small? I am thinking that this can be increased, perhaps to a limit of 6’ depending on the wall capacity (also needs to be small enough to ensure the wall mainly spans between the pilasters). To determine this would I just find out what the distance a 6” concrete slab can span before needing horizontal reinforcement (the 6” wall only has the vertical bars so it has no contribution from horizontal bars)?
Also can it be safe to assume and design these pilasters to act as columns that will take the full overturning moment and bending moment from the vertical direction that the wall was originally meant to take?
Also as shown in the sketch the external wall is resting on some compacted sand (quite hard material, needs a jack hammer or something to break it). I assume I will need to take the vertical load from the external wall on that piece of sandy material as a surcharge acting on the 6” wall also when determining the bending moment in the stem and overturning moment? Please correct me if I am wrong.
I am trying to completely avoid demolishing the existing wall and would prefer to reinforce it some way. The architect is fine with the addition of pilasters.
Any ideas or feedback/advice for this method would be greatly appreciated.