What procedures are recommended for:
1) stamping a date received
2) stamping a date reviewed
on shop drawings?
Does your company do every sheet, just the front sheet or just the transmittal? If just the transmittal, then I would think at a minimum that it should list every sheet and the date issued. If just the front sheet, does it have an index that lists all other sheets?
What are the implications for liability?
1) stamping a date received
2) stamping a date reviewed
on shop drawings?
Does your company do every sheet, just the front sheet or just the transmittal? If just the transmittal, then I would think at a minimum that it should list every sheet and the date issued. If just the front sheet, does it have an index that lists all other sheets?
What are the implications for liability?