Ndimo
Chemical
- Jan 11, 2005
- 13
Good day to all,
In the process of trouble shouting a mud disposal system, I found that although the discharge point has an elevation below the suction point; thus giving a negative static head, there is a hill in between wich is 100 ft above suction elevation. How could I take in account that hill in the system determination ?
Thanks
In the process of trouble shouting a mud disposal system, I found that although the discharge point has an elevation below the suction point; thus giving a negative static head, there is a hill in between wich is 100 ft above suction elevation. How could I take in account that hill in the system determination ?
Thanks