Structures33
Structural
- Feb 22, 2007
- 111
hey there - I have two scenarios regarding the sloping of concrete slabs for which I would like some opinions.
1. typical concrete slab on grade (6" or 8") used for maintenance facility type application; has multiple floor drains to which we need to slope the slab. The building dimensions vary but let's say 75'x50' for this example. I'm looking for opinions on methods for sloping the slab to the drains - slope entire floor maintaining thickness or slope entire floor with varying thicknesses... or feather at the drain? There will not be regular "traffic" on the slab but it will see an occasional truck or forklift.
2. bottom slab (approx 2'-10" thick) of concrete basin containing water or wastewater; multiple "trains" divided by 2'-0" walls - each one has it's own drain. Approximate layout is four 40' wide trains x 100' long (side by side so they share one base). Right now we specify grout fill to acheive the slopes. What are opinions on this?
Thanks for sharing any opinions and/or experiences
1. typical concrete slab on grade (6" or 8") used for maintenance facility type application; has multiple floor drains to which we need to slope the slab. The building dimensions vary but let's say 75'x50' for this example. I'm looking for opinions on methods for sloping the slab to the drains - slope entire floor maintaining thickness or slope entire floor with varying thicknesses... or feather at the drain? There will not be regular "traffic" on the slab but it will see an occasional truck or forklift.
2. bottom slab (approx 2'-10" thick) of concrete basin containing water or wastewater; multiple "trains" divided by 2'-0" walls - each one has it's own drain. Approximate layout is four 40' wide trains x 100' long (side by side so they share one base). Right now we specify grout fill to acheive the slopes. What are opinions on this?
Thanks for sharing any opinions and/or experiences