sgsibob
Geotechnical
- Apr 15, 2002
- 31
Can someone please enlighten me about the constructibiity pitfalls of top-down lagging of soldier pile walls? If, for example, a lift is excavated 5 ft with lagging in place, what keeps the lagging there -- earth pressure on the back side of the lagging? Suppose the wall is 50+ ft high -- is it reasonable to expect that the earth pressures would be adequate to pinch all that lagging so none of slips? Also, suppose the vertical height of drilled shaft hosting the lagged portion of the piles is backfilled with weak cementitious material, such as soil cement or a 1/2 sack slurry...how is this material removed from between the flanges (and from the front flange, for that matter) so the lagging can be installed? Finally, if the wall is tied back, how does the lagging accommodate the space between the flanges lost by the tieback and web stiffeners? Be as verbose and comprehensive as you like -- I am interested in all the "war stories" also. Thanks.