Hi All,
I did an analysis on a equipment. The equipment is welded to the ground plate at 16 points/Nodes (N1, N2...N16). The analysis under 3 different loading scenarios give 3 outputs as attached. I am doing some hand calculations for welding at these nodes. The TOTAL LOAD (highlighted in yellow) in any one direction differs in the 3 load scenarios. Any advice which one of the 3 loading scenario (worst case) should I pick for doing my hand calculations?
Thanks in advance.
Regards,
HD
I did an analysis on a equipment. The equipment is welded to the ground plate at 16 points/Nodes (N1, N2...N16). The analysis under 3 different loading scenarios give 3 outputs as attached. I am doing some hand calculations for welding at these nodes. The TOTAL LOAD (highlighted in yellow) in any one direction differs in the 3 load scenarios. Any advice which one of the 3 loading scenario (worst case) should I pick for doing my hand calculations?