bridgebuster
Active member
- Jun 27, 1999
- 3,969
Does anyone know of any studies regarding the validity of the ENR pile driving formaula, Safe Load = (2WH)/(s+1) and what Factor of Safety was used? I took the formula from "Foundations of Bridges and Buildings", 1914 edition, by Henry S. Jacoby.
Here's what's going on: I got sucked into a bridge rehab project - of course no job number, but it's Lent and alms giving is good - a steel viaduct (circa 1920's) with a non-operational double leaf bascule main span, supported on timber piles approximately 70' long. The leafs (or is it leaves?) were locked in the 50's; the machinery was removed, and the pits have been flooded since.
The owner wants to fill the pits with lightweight concrete. The PM (not a bridge guy) and his design team (including geotechs) are opposed since they don't know the pile capacity. They assume it's 20, maybe 30 T (which is not unreasonable for a timber pile) and believe the piles are only loaded to 20 T or maybe 26 T. (This has been going on for 3 years now; that's why I fustrated.)
In the original drawings I found a note stating capacity is achieded with a 3000 # hammer, dropped 15 feet; 1/2" displacement for the last five blows. If I use the ENR formula and the plan data, I arrive at 30 T capacity; I would assume the ultimate would have be at least twice this number. The soil is a thick organic layer on top of sand.
Thanks
Here's what's going on: I got sucked into a bridge rehab project - of course no job number, but it's Lent and alms giving is good - a steel viaduct (circa 1920's) with a non-operational double leaf bascule main span, supported on timber piles approximately 70' long. The leafs (or is it leaves?) were locked in the 50's; the machinery was removed, and the pits have been flooded since.
The owner wants to fill the pits with lightweight concrete. The PM (not a bridge guy) and his design team (including geotechs) are opposed since they don't know the pile capacity. They assume it's 20, maybe 30 T (which is not unreasonable for a timber pile) and believe the piles are only loaded to 20 T or maybe 26 T. (This has been going on for 3 years now; that's why I fustrated.)
In the original drawings I found a note stating capacity is achieded with a 3000 # hammer, dropped 15 feet; 1/2" displacement for the last five blows. If I use the ENR formula and the plan data, I arrive at 30 T capacity; I would assume the ultimate would have be at least twice this number. The soil is a thick organic layer on top of sand.
Thanks