512Engineer
Civil/Environmental
- Mar 17, 2016
- 3
I’m designing a wastewater lift station with VFD’s. I have not found any printed guidelines, etc. about sizing the minimum working volume for the wet well when VFD’s are used. We are flow matching to an extent, however, it would seem as though I would need a design basis for a minimum volume.
The state requires me to have a 15 minute cycle time for my pumps. The pumps can handle 4 minute cycle times. My idea was to get a variance from the state since I’m using VFD’s and then use a factor of safety of 2 and design around an 8 minute cycle time. This will reduce my wet well volume and still protect the pumps. Does that sound reasonable? The other question I have is what Q, should I design around? For constant speed pumps, we design around the total Q, however, this seems really conservative for stations with VFD’s.
Do you have any guidance or lessons learned that you can share?
Many Thanks.
Charles
The state requires me to have a 15 minute cycle time for my pumps. The pumps can handle 4 minute cycle times. My idea was to get a variance from the state since I’m using VFD’s and then use a factor of safety of 2 and design around an 8 minute cycle time. This will reduce my wet well volume and still protect the pumps. Does that sound reasonable? The other question I have is what Q, should I design around? For constant speed pumps, we design around the total Q, however, this seems really conservative for stations with VFD’s.
Do you have any guidance or lessons learned that you can share?
Many Thanks.
Charles