My take...
1 Deck was poured.
2 Truss was poured.
3 Canopy was poured.
4 Blisters were poured. At his point, all concrete, & steel is at equilibrium, with no forces to cause cracks.
5 Once concrete was aged, post tensioning was started while still in supported mode.
6 Then shoring was removed, leaving only end bearing supports. I believe this is when #11 cracks 1st showed up, due to the flexible #11 rebar in shear
interface to deck. It cracked, & jammed #11 into #12. #12 was more solidly restrained in place due to #12's to deck rebar in tension formation.
You can still see #12 to deck rebar at the end of the deck, with the j-bends on them that turned upward into the column. These, combined with the visible
Box out area under #12, made for a more rigid deck connection. The rebar ran in a more parallel interface to deck, which put it in tension, vs #11 rebar
in shear.
6 Once it was time to move, diagonal/post tendons were pre-stressed to allow inward load bearing on transporters. At this point, the crack most likely
stayed open.
7 Bridge was traversed across uneven road ( curb on south end , plus divider curb at mid/northern side) with several moments of inward load bearing, while
they shuffled bridge off center. It's evidenced in one of the time lapse videos. In effect, this may actually have closed the cracks. Due to the extreme
cantilever, it resulted in more weight than the tendons could bear. The tendon calc. was base on an outer bearing point.
8 Bridge is set in place, with crack still closed up, due to additional surface friction from #11 tendons at 560 kips.
9 I'm thinking at this point that once bridge was set, the next step was to de-tension #11 tendons. If this was not the case, why else would have #11's
blisters have been grouted? It was the planned course of action by design.
Remember, they had to jack hammer the opening to get to the tendons for the tensioning, that Rubio later said they were going to do to close the
cracks.
10 Jack hammered out grout, & reapplied tension to close the crack.
11 Bridged collapses while applying tension to last #11 tendon.
The logic behind applying tension to #11 to close cracks, may have come from the likelihood that it probably did just that when it was moved, & set. So,
it worked before, why not again!
The basic push/pull loads from shoring, to transport, to being set, to releasing tendons, to applying tendon tension, at #11's base contributed to bridge
collapse. In the end, I believe that #11 short fillet bore the brunt of horizontal loads, exploded.