Tilas
Mechanical
- Feb 17, 2013
- 48
Hi,
I have an API 610 pump being installed at site. Before we could go with the final alignment, we would need to align the piping with the pump flange.
There is a chance that the piping might need heating or cut and weld to have the flange gap and angularity to within API 686 criteria (in case moving of the supports is not enough to have the pipe alignment within tolerance).
=======
API 686 4.6.3 : For piping flange outer diameters smaller than 25 cm (10 in.), the flanges shall be parallel to 250 micrometers (0.010 in.) or less. For raised face flanges, feeler gauge readings shall be taken at the raised face.
API 686 4.6.4: Flange face separation shall be within the gasket spacing ±1.5 mm (1/16 in.). Only one gasket per flanged connection shall be used.
========
My question would be (considering that all the pipe spools were hydro tested already prior to pipe alignment):
1. In case they heated the pipe flange or do some small cut and re-weld to the pipe flange to get the gap to within the API 686 tolerance , would they need to dismantle the last spool again for hydro testing (spool connected to be connected to the pump nozzles).
3. Can we just opt for a 100 RT in order not to remove the aligned pipe in its position instead of doing a hydrotest if we are to cut and re-weld or heat?
2. If they remove the last spool for hydro test I am afraid that they would have difficulty on getting the required flange gaps and angularity again.
Please let me know if how did you did it for your API 610 pumps during installation.
Thanks in advance.
Tilas
I have an API 610 pump being installed at site. Before we could go with the final alignment, we would need to align the piping with the pump flange.
There is a chance that the piping might need heating or cut and weld to have the flange gap and angularity to within API 686 criteria (in case moving of the supports is not enough to have the pipe alignment within tolerance).
=======
API 686 4.6.3 : For piping flange outer diameters smaller than 25 cm (10 in.), the flanges shall be parallel to 250 micrometers (0.010 in.) or less. For raised face flanges, feeler gauge readings shall be taken at the raised face.
API 686 4.6.4: Flange face separation shall be within the gasket spacing ±1.5 mm (1/16 in.). Only one gasket per flanged connection shall be used.
========
My question would be (considering that all the pipe spools were hydro tested already prior to pipe alignment):
1. In case they heated the pipe flange or do some small cut and re-weld to the pipe flange to get the gap to within the API 686 tolerance , would they need to dismantle the last spool again for hydro testing (spool connected to be connected to the pump nozzles).
3. Can we just opt for a 100 RT in order not to remove the aligned pipe in its position instead of doing a hydrotest if we are to cut and re-weld or heat?
2. If they remove the last spool for hydro test I am afraid that they would have difficulty on getting the required flange gaps and angularity again.
Please let me know if how did you did it for your API 610 pumps during installation.
Thanks in advance.
Tilas