I've just caught up with the links to the ARES Rail Energy Storage Scheme. My first thought was to check the calendar - but no, it's not April 1. Then I wondered why on earth you would consider this over technologies such as Pumped-Storage Hydro?
Thinking about it, though, I guess I can see the logic in the right circumstances - the technology would work where you have limited gradients (steel-wheel-on-rail doesn't work well on steep grades), plenty of horizontal space but limited elevation to play with, limited amount of energy storage requirement - and no suitable water / dam sites.
However, where there is a suitable elevated water storage site above a lower pond, it is hard to see how this technology could compete with Pumped-Hydro for capacity (scale) or efficiency.
E.g. the Ares Nevada project is looking at 50 MW / 12.5 MW.hr capacity (15 minutes storage at full capacity). Existing Pumped-Storage schemes are already in the multi-GW range, with tens of GW.hr storage (i.e. able to run at full capacity for hours, not minutes), and with round-trip efficiency > 80%.
Thinking about it, though, I guess I can see the logic in the right circumstances - the technology would work where you have limited gradients (steel-wheel-on-rail doesn't work well on steep grades), plenty of horizontal space but limited elevation to play with, limited amount of energy storage requirement - and no suitable water / dam sites.
However, where there is a suitable elevated water storage site above a lower pond, it is hard to see how this technology could compete with Pumped-Hydro for capacity (scale) or efficiency.
E.g. the Ares Nevada project is looking at 50 MW / 12.5 MW.hr capacity (15 minutes storage at full capacity). Existing Pumped-Storage schemes are already in the multi-GW range, with tens of GW.hr storage (i.e. able to run at full capacity for hours, not minutes), and with round-trip efficiency > 80%.