Could someone provide some insight on the difference between active and passive synchronization.
I have a project with closed transition were everything was designed around "pasive" synchronization and the Generator vendor is stating that they cannot do that and they only do "active" synchronization.
What are the differences?
Are there standard ways to bridge the gap or to make this work.
I have a project with closed transition were everything was designed around "pasive" synchronization and the Generator vendor is stating that they cannot do that and they only do "active" synchronization.
What are the differences?
Are there standard ways to bridge the gap or to make this work.