Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Miami Beach, Champlain Towers South apartment building collapse, Part 13 44

Replies continue below

Recommended for you

> All the while, you say something about being an engineer or just forget that your profile clearly identifies you as a Professional Engineer.

Good thing I'm not a professional engineer eh :)

I'm still interested in the unusual shape of the punching shear breaks and if I get around to it I will make a longer post with some (non professional, suck it Florida engineering board) opinions. Related to that, I think someone posted a document early saying how the pouring of the columns and the slab above worked. I'm interested as to whether the column was built first and the slab then poured around it (so there's a vertical joint around the column) or if column + slab above was all done at once.
 
The board takes this very seriously, but they are strangely quiet... same for California, it seems.

Rather than think climate change and the corona virus as science, think of it as the wrath of God. Feel any better?

-Dik
 
Normal practice is to pour the Column first, stopping the pour an inch or so below the deck form. The column will shrink a little as the slab is prepared over the next few days.

If you pour the slab and column at the same time, you risk a crack at the top of the column when column shrinking occurs and downward movement of the slab is restrained by the shores.


Shear calculations consider the column support size and shape as well as the deck thickness and the cold joint does not play into it.

Normal failure will leave pieces of the slabs at the top. Failure straight down without leaving stubs from the slab sticking out is very unusual.

As to the Florida board, I doubt they would take offense to unofficial posts on a social media site for engineers. It is not a report for the Public.

Regards,

mojojohn
 
Red... columns and slabs often have different concrete strengths and other properties.

Rather than think climate change and the corona virus as science, think of it as the wrath of God. Feel any better?

-Dik
 
I'm surprised no-one in the color-glossy-infogram and sexy-3D-animation biz has picked up on the sub-spec rebar yet. Has anyone found a 60 grade rebar marking in any pic?
 
I uploaded my latest video last night which talks about how much water we've noticed pooling on the roof of both Champlain Towers South and North buildings a year ago shown on drone flyovers on dry days.


.
.
Water_on_condo_roof_wlhd1p.jpg
 
AusG said:
I'm surprised no-one in the color-glossy-infogram and sexy-3D-animation biz has picked up on the sub-spec rebar yet. Has anyone found a 60 grade rebar marking in any pic?

Is Gr 60 what was required/specified? Most of the bar in the images above appears to be grade 50. Although the pics aren't stellar.
 
> Normal failure will leave pieces of the slabs at the top. Failure straight down without leaving stubs from the slab sticking out is very unusual.

Yeah, that's why it's so interesting. It's not even straight down, the columns have been 'pinched' around the failure point. I feel like this has some interesting things to say about the material properties (rebar placement as well) there but I want to check I am not a total idiot before going into that :)

> Normal practice is to pour the Column first, stopping the pour an inch or so below the deck form. The column will shrink a little as the slab is prepared over the next few days.

The slab is then a complete, unbroken surface, right? There is no column of concrete going 'through' the slab (though there is rebar doing that if there will be another column above the slab - not true on the pool deck in this case)? That's my understanding from previous posts as well.

building-pour-order_wypxnd.png


Something like this. Rebar in the slab optional if you're in Florida in the 1980s ...
 
The one thing I've always wondered about when they're pouring concrete for the columns if they stop at the end of their pour and I don't know how long they wait maybe a day or two? What do they do about cold joints forming? Are they required to use any kind of primer in between or bonding agent or anything like that? That's what I've always worried about is how do you continue that column all the way up as one homogeneous material?
 
Red corona

Your understanding is correct.

Jeff

No primer or bonding agent.Does act monolithic due to steel passing through joint.
 
Jeff Ostroff said:
What do they do about cold joints forming?

There are cold joints for sure; typically the term 'construction joint' is used, as they are planned. 'Cold joint' implies a joint between pours that should be monolithic and only exists because someone screwed up.

All construction joints will have steel passing across them and will usually be chipped or roughened for mechanical engagement between poured sections.
 
Red Corona said:
Yeah, that's why it's so interesting. It's not even straight down, the columns have been 'pinched' around the failure point. I feel like this has some interesting things to say about the material properties (rebar placement as well) there but I want to check I am not a total idiot before going into that :)

I'm not so sure that it's a huge indicator.

A single punching shear failure in a big matrix of columns will have widespread effects- namely the doubling of the unsupported length of the slab between columns surrounding the failure. The slab may then fail in a few different modes, depending. If the slab cross section is strong enough to stay standing across the new unsupported length, you might see punching shear on surrounding columns, too. If it isn't strong enough to self-support across the new length, however, the slab at adjacent column/slab nodes might fail in bending, or in tension. It may only take one punching shear failure (ie punching shear failure at a single node in the matrix) to induce complete failure of the slab, but that doesn't mean every node is going to fail in shear. In order to really know, you'd need pictures of EVERY column/slab node to figure out how they each failed. We only have a few.

Not saying you're wrong.. just saying that IMHO we are short on information to support a big conclusion from the fact that a few nodes didn't fail in a fashion we normally associate with regular punching shear.
 
@Reverse_Bias I cannot find that NYT article for the life of me, tried searching on their site multiple was related to surfside but can't find an article from 9/22. Got a link to the article?
 
from the CRSI:
Each Individual Reinforcing Bar is Manufactured with a Series of Individual Markings:

The first letter or symbol identifies the producing mill.
The next marking is the bar size.*
The third marking symbol designates the type of reinforcing steel — usually either "S" for carbon-steel (ASTM A615) or "W" for low-alloy steel (ASTM A706).
Finally, there will be a grade marking (60, 75, 80, 100, 120) or by the addition of one line (60) or two lines (75), three lines (80, 100), or four lines (120) that must be at least five deformations long.
 
Have we any indication as to why beams 33, 34, and 35 are still left on the slab?

Precision guess work based on information provided by those of questionable knowledge
 
Problem is Charlie they have a pay wall to read their stories, so I can't read it.
 
Is “Here Are 11 Serious Flaws Discovered In the Surfside Tower” available online? It does not get returned in a search. And the image itself does not produce a hit in a reverse image search. Charlie indicates that it is page A12 from the print edition. The link he provided shows the interactive 3D model that we already saw about a month or so ago.

FWIW, like some other publications, the NYT counts number of views by IP address rather than by setting cookies. So clearing your cache will not reset the monthly count because it’s maintained server side. A typical way to avoid this limitation is to use a VPN, which can unfortunately slow your browsing by having narrowed your available bandwidth. To avoid cookies that other sites set, you can use Firefox to browse, and then erase your cache at the end of every session.
 
Here's a higher quality readable version of the article for download. Eng forums mangled it when I inserted the image into the post.
The only internet record of the article I found was the tweet from the author. But link provided in the tweet is to the Sept 1st interactive article not to the image in the tweet. I assume the graphic was the print only version, with mostly the same information.


 
Status
Not open for further replies.

Part and Inventory Search

Sponsor